2006 INITIAL SCHOOL RESOURCE PACKAGE FUNDING DETAIL SHEET

As at: 30-Mar-2006

Summer Bay District High School

Budget Centre: 999
 

Esplanade Street, Summer Bay 7216    Phone: 03 6272 4665    Fax: 03 6272 4668

 

General Support Grant
Per Capita: $22,481.68
Educational Needs: ** $10,728.74
Distance: ** $3,775.28
Size of Centre: ** $15,523.68
Isolation: ** $0.00

Total :

$52,509.38

 

 
Maintenance and Minor Works
Maintenance and Minor Works:

$26,239.20

   
Utilities Allocations
Electricity: $21,617.89
Other Energy: $0.00
Excess Water: $0.00

Total :

$21,617.89
   
Student Assistance Scheme

Total :

$3,056.20

   
Discretionary Levy Compensation

Total :

$1,591.20

   
Other SRP Funding
Kindergarten Aides: $6,426.38
Bass Strait Travel: $0.00

Total:

$6,426.38

   
Miscellaneous Type Amounts
Teacher Staff Sickness Relief: $6,618.06
Initial Cluster Transfer: $4,972.95
Information & Communications: $0.00
Early Childhood Class Size Funding: $2,415.22
Literacy Program: ** $11,460.16
Country Areas Program: ** $9,106.29
Balance from Previous Year: $4,395.23

Total:

$38,967.91
   
Total SRP Funding as at
30-Mar-2006: $150,408.16
   
Includes Notional Cluster Allocation 30-Mar-2006:
Total of ** as above $50,594.15
  The calculation of your current SRP entitlement is based on the following statistics:
       
  2006 School Indicies   2006 Residences
  Educational Needs: 62.54   Owned: 3
  Distance: 82   Leased: 0
  Size of Centre: 6      
  Isolation: 0      
  AMPS: $25,629      
  FECA: 2428m2      
  Remoteness Ranking: 3      
           
  2006 Enrolments (FTE)   2006 STAS Approvals
  Early Special: 0.00   Early Special: 0
  Kindergarten: 3.5   Kindergarten: 0
  Prep to Year 6: 44.0   Prep to Year 6: 10
  Year 7 to Year 10: 29.0   Year 7 to Year 10: 8
  Senior Secondary: 10.0   Senior Secondary: 6
 

Total:

86.5

 

Total:

24

           
 

FTE Basis:

 

STAS:

  First Term Census Enrolments   Interim 2006 Numbers
           
           
  Senior Secondary Adjustment

1.10000

 
           
  Previous Years Utilities and Sickness Relief
  Year: 2005   2004  
  Electricity: $23,500.15   $22,707.16  
  Other Energy: $0.00   $0.00  
  Excess Water: $0.00   $0.00  
  Sickness Relief: $0.00   $0.00  
           
  Report Notes
  The Interim 2006 SRP Allocations are based on:
  2006 Indicies
  2006 Predicted Enrolments
  2006 Interim SRP Rates

 


Cash/Non-Cash Summary   2006 SRP Instalment Summary
  Cash Non-Cash Total   Scheduled Instalments  
Budget: $56,908.01 $93,500.15 $150,408.16   February: $15,580.52  
Receipts: $15,580.52 $93,500.15 $109,080.67   May: $0.00  
Outstanding: $41,327.49 $0.00 $41,327.49   June: $0.00  
          July: $0.00  
          December: $0.00  
          Final Grant: $0.00  